OTHER INFORMATION
Lazarus Zrt. has closed some of its futures positions
Lazarus Zrt. has closed some of its futures positions
As parts of Geothermal Project of Miskolc, works to cover the geothermal heat transmission lines and assess operating safety have been started Early January saw the commencement of the last works associated with the implementation of the Geothermal Project of Miskolc during which engineering loading tests, works to cover transmission lines and conduct the preceding […]
In connection with Synergon Group’s data park investment, PannErgy Plc is developing an air-conditioning and heating solution based on the exploitation of geothermal energy. As it has already been planned, PannErgy Plc (PannErgy) will construct and supply the airconditioning and heating solution for Synergon Group’s data park investment, which will set the energy supply of […]
The head of the Managing Authority of the Economic Development Operational Programme (GOP) has esteemed the proposal of PannErgy’s subsidiary, Miskolci Geotermia Zrt. to be worthy of a HUF 162,499,883 non-repayable grant.
Grant agreement signed by PannErgy’s subsidiary PannErgy Plc’s subsidiary, Kuala Kft. has signed the grant agreement for its project to be implemented within the framework of the Environment and Energy Operational Programme (KEOP)
The submergible pumps and wellheads to be used at the Mályi production wells have been installed – with the performance of the pressure tests on the pipe sections between the wells and the district heating center Probably the most important elements of the technological system known as the Geothermal Project of Miskolc, i.e. the submergible […]
Benji Invest Kft. has increased its stake in PannErgy Plc
New payment has been made in connection with the PannErgy subsidiary, Miskolci Geotermia Zrt’s grant application submitted and awarded in the framework of the KEOP – 2010 – 4.7.0 Environment and Energy Operational Programme, New Hungary Development Plan, entitled “Economic and Social Renewal in Miskolc”.
Prepayment connected with the second part of the two-stage grant application entitled “Economic and Social Renewal in Miskolc” has been made to PannErgy’s subsidiary, Miskolci Geotermia Zrt.
Site inspection before the last phase of the Geothermal Project of Miskolc Before the closing phase of the Geothermal Project of Miskolc, PannErgy Plc’s management held a site inspection where the heat exchanger deployed at the Avas hydraulic station was viewed. During the site inspection, the Company’s management visited the District Heating Center of Kistokaj, […]
New payment has been made in connection with the PannErgy subsidiary, Miskolci Geotermia Zrt’s grant application submitted and awarded in the framework of the KEOP – 2010 – 4.7.0 Environment and Energy Operational Programme, New Hungary Development Plan, entitled “Economic and social renewal in Miskolc”.
New payment has been made in connection with the PannErgy subsidiary, Miskolci Geotermia Zrt’s grant application submitted and awarded in the framework of the KEOP – 2010 – 4.7.0 Environment and Energy Operational Programme, New Hungary Development Plan, entitled “Economic and social renewal in Miskolc”.
For the period of Q1-3 of 2012
In the framework of the Geothermal Project of Miskolc, an independent pressure test on the primary section and secondary loop of the geothermal heat transmission line has been launched, to be followed by works to cover the pipelines and restore the environment. Upon the completion of one of the major sets of mechanical engineering works, […]
PannErgy Plc’s subsidiary, Kuala Kft. has been awarded with a non-repayable grant for its proposal that was submitted within the framework of the grant application scheme announced as a part of the New Széchenyi Plan’s Environmental and Energy Operational Programme, and entitled “Subsidy of the preparing and developing activities of the geothermal based heat and […]
Connection point between the grid of the Geothermal Project of Miskolc and the existing transmission line linking the MIHŐ Heating Plant and the Avas district heating center has been completed. In parallel with the pipeline construction, the technical implementation works covering the last phases of the Geothermal Project have been continued. In addition to the […]
The testing of reinjection well KIS-PE-02 has been concluded, and in parallel the technical, mechanical engineering works associated with the implementation of the Geothermal Project of Miskolc have been commenced. Recent days have witnessed the testing of reinjection well KIS-PE-02 of Kistokaj and the evaluation of the resulting data, as well as the installation of […]